"Aganneftegasgeologia" is developing the infrastructure of the oilfields of the Nizhnevartovsk Region

Options

"Aganneftegasgeologia" is developing the infrastructure of the oilfields of the Nizhnevartovsk Region

At Roslavlskoye there are built a double-curcuit hgh-voltage  6 kV power line from "Roslavlskoye" substation to well pad No 6, two high-voltage 6 kV lines from "Lesnaya" substation to well pad No 17. To supply power to well pad No 1 of Yuzhno-Roslavlskoye oilfield another high-voltage power line was built. This line helped to replace diesel power with centralized power supply.
The problem of power supply to well pad No 1 at Mokhtikovskoye oilfield was also resolved.
On the whole in the first half of 2010 the subsidiary of "RussNeft" has built more than 14 thousand meters of high voltage lines. Active infrastructure development of the oilfields is going on. At present a high-voltage 6 kV power line is under construction at Yeguriakhskoye oilfield, says the press-servise of the company.