“Vologdaenergo” reconstructs partially 110/35/10 kv substation “Pogorelovo”

Options

“Vologdaenergo” reconstructs partially 110/35/10 kv substation “Pogorelovo”

The project is implemented in the framework of the technological connection implementation of power receivers of “Gasprom invest West”, LLC to the grids of the enterprise.
To implement the external power supply of compressed air station “Novoyubileynaya” of the gas pipeline “Ukhta-Torzhok”, two new cubicles 10 kv of K-63 type with vacuum circuit breakers BB-TEL of “Tavrida Electric” production were installed at 110/35/10 kv substation “Pogorelovo” in 10 kv indoor switchgear (ISG).
Nowadays the new equipment of the substation is fully put into operation. Pursuant to the contract of technological connection branch “Vologdaenergo” reserved the total capacity 2800 kW for the consumer at the supply equipment.  The cost of the service by the contract has amounted to RUR 5 million.