IDGC of the North-West transfers a mobile 110/10/6 kilovolt substation from Vologda to Arkhangelsk

Options

IDGC of the North-West transfers a mobile 110/10/6 kilovolt substation from Vologda to Arkhangelsk

They decided to transfer a mobile 110/10/6 kilovolt substation from Vologda to Arkhangelsk. Chief engineer of JSC “IDGC of the North-West” Georgy Turlov signed the corresponding order.
“A mobile substation is given for the temporary usage to branch of IDGC of the North-West “Arkhenergo” for the period of reconstruction of substation “Privokzalnaya” in  Arkhangelsk which is a closed feeding centre”, - explained Deputy Chief engineer by the operation and technical development Gennady Alexandrov. “A necessity of a mobile substation transfer from Vologda is caused by an existing power deficit in Arkhangelsk. Another way to end restrictions of consumers of the central part of the city is impossible”, - he said .
A relocation of modules of the mobile substation from Vologda to Arkhangelsk will be made by railway. The mobile substation is planned to be launched in August of the current year.

RU

Full version

Close
Яндекс.Метрика