“Engineering Center UES” completed construction of foundation at Sredneuralskaya GRES power plant

Options

“Engineering Center UES” completed construction of foundation at Sredneuralskaya GRES power plant

Currently, power floor is under construction in the main building and work on construction of circulating water pump station is in progress. After completion of concrete work, specialists from “Engineering Center UES” will start connection of the power plant to external grid, will connect to the gas supply line; they will ensure electric and thermal power output. It is planned to complete the work in quarter3 of the year 2010.
Let us remind that “Engineering Center UES” was awarded the construction contract for work at the new CCPP-410 МW power unit of Sredneuralskaya GRES power plant in January 2009. In accordance with the contract, the company provides for construction of foundation for the CCPP-410 МW power unit main building, CW pump station, cycle makeup water treatment facility (for CCPP-410), foundations for industrial and domestic wastes treatment facility, booster compressor station, foundations for transformers and transformer tracks. The project Customer is OAO “Enel OGK-5”, EPC-contractor is a Spanish engineering company Iberdrola.
For project implementation, six subcontracting organizations and involved. At this time, about 150 workers are engaged at the construction site.
Apart from construction and installation work at CCPP-410 MW unit, “Engineering Center UES” continues work at the site under two additional agreements – with Iberdrola for construction, supply and installation of buried lines and with OAO “Enerl OGK-5” for construction, installation and startup-and-adjustment work on the utility lines. Currently, the following work is in progress: construction of foundations for electric and thermal power output rack from CCPP, construction of water supply and sewage lines and construction of fire pump station.

RU

Full version

Close
Яндекс.Метрика