JSC “Yenisei TGC (TGC-13)” Starts 2010 Repair Program

Options

JSC “Yenisei TGC (TGC-13)” Starts 2010 Repair Program

Current repair is to be carried out at 69 steam boilers, 5 water boilers, and 27 turbine units.
The Company’s heating system provides for works on replacement of 25.6 km of heating grids including over than 18 km in Krasnoyarsk over the term between heating seasons.
Most large-scale repair works are planned at the Nazarovo GRES including average repair of 3 energy units, at the Abakan CHP including capital repair of 1 turbine and 3 boiling units, and at the Krasnoyarsk CHP-1 including capital repair of 4 boilers and 1 turbine. Capital repair of a boiler and average repair of a turbine are planned at the Krasnoyarsk CHP-2.
One shall note increase of loading at energy capacities of all electric stations located at Siberia and the Republic of Khakassia starting from August 2010 which was connected with the accident at the Sayano-Shushenskaya HPP. To prevent possible failures in operation caused by long-term work with maximum loading, the Yenisei TGC plans to increase the number of equipment pieces at CHPs and GRESes subject to be repaired in 2010 in comparison with the number in 2009.
“We will put out attention to repair of equipment operating with maximum loading this year,” said Evgeniy Zhadovets, the Executive Director of JSC “Yenisei TGC (TGC-13)”.

RU

Full version

Close
Яндекс.Метрика